“Litgrid” system control and data center
In May 2018, general contractor “Conres” was entrusted with the construction of “Litgrid Management and Data Security Center” – a key economic project, recognized by the Government in September 2015. The value of the investment is ~10 mln. Euros. sutartį su elektros perdavimo sistemos operatoriumi AB „Litgrid“ dėl duomenų ir valdymo centro statybų. Sutarties vertė – ~10 mln. Eur.
CONRES
PLC „Litgrid“
Lithuania
JSC „Unitectus“
Project area:
5 669 m2
Investment:
10 million euros
Construction duration:
2018 05 - 2019 12
According to the Ministry of Energy, the center will ensure a more stable and secure operation of the country’s energy system and management of transmission flows. After synchronization, this center will control the frequency of the electrical system and provide the required physical and cyber security of the system control center.
The construction of the new center (building) will allow proper perimeter protection and room segmentation. There will be an electronic access control system providing the necessary mandatory return function, a vehicle checkpoint, high reliability mechanical barriers, duplicated fiber optics and other security features. The new building will also house system management and data centers, and provide appropriate facilities for staff working in system management and other administrative departments.
“This is where the whole frequency of the system is going to be controlled from and people will make decisions here. At Žvejų street, this is done as agreed in the current IPS/UPS synchronous zone. At the moment, the agreement is that centralized management is all done in Moscow, whereas in Europe there is already a decentralized approach to it. That’s what we’re going to do here – decentralized it,” in an interview with BNS said Mr. Virbickas.
Materiality
- Energy efficient aluminum-glass facades
- Natural wood veneer wall finish
- Stabilized moss
Special features
- Center is important for the Baltic States in synchronizing power systems with continental Europe
Ecology
- Geothermal heating
- EV charging stations
- Planted roof
Managed risks
- Work area in a large amount of underground communications with 110kV Eeectrical networks
Inovations
- High level of acoustic comfort
Energy
efficiency class:
A+
Building height:
18 m
Number of floors:
4
Building purpose:
Specialized
The new center is important for the Baltic States in synchronizing power systems with continental Europe. The new center will be operational by the end of the synchronization process in 2025.
Daivis Virbickas, CEO of “Litgrid”