fr lt en

“Ikarai” Liquid Fertilizer Plant, Kėdainiai FEZ

During the three phases of construction, more than 3 million euros was invested in the fertilizer production and logistics center. Conresta, the general contractor of the first phase, built a nearly 2,000 sq. m. production and storage building. This is the first and a really significant investment in the Kėdainiai FEZ, and is very important for Lithuanian farmers, as until now only the crematorium (which was built before the recognition of the industrial park as a free economic zone) operated in the area.

Finished
General contractor

JSC "Conresta"

Client

JSC „Ikarai“

Country

Lithuania

01

Construction started:

2016 11

02

Construction period:

8,5 months

03

Project area:

2 000 m2

In the Free Economic Zone of Kėdainiai, the company has invested in liquid and slurry fertilizer production complex. There is also a driveway and paved railway loading area in the territory of almost 4 ha. Production and storage buildings, as well as raw material and production warehouses for the production of liquid fertilizers were built. Therefore, the structures to be built had to be particularly resistant to the alkaline and acidic environment.

During the 2nd and 3rd stages of construction, a heated logistics warehouse and two additional production lines were installed, allowing to increase production volumes. A modern 300-square-meter laboratory has been set up next to the plant to conduct in-depth studies of plants growing in artificial light, showing how liquid fertilizers affect plants and what active ingredient is best for individual crops. It produces about 10 thousand tons of liquid complex fertilizers each year.

04

Special purpose:

Storage of liquid, slurry fertilizers

05

Modern laboratory

300 m2

Building the plant was a crucial step for us in consolidating our position as a liquid fertilizer manufacturer. Considering the good infrastructure, favorable attitude of the territory manager and the municipality, we have chosen Kėdainiai FEZ. Besides, Kėdainiai FEZ is convenient in terms of logistics.

Remigijus Streckis, the CEO of “Ikarai”

Other projects

Eurovaistinė logistics centre

Stage I of Ukmergė Industrial Park

Refinis factory

Omniva parcel sorting terminal

Lidl Lietuva (Lidl Lithuania) logistics centre

Finished

Modernisation of the Medininkai Border Crossing Point

The construction of Vilnius Combined Heat and Power Plant using municipal waste and biofuel

Construction of the KG Constructions Group factory and office building

Finished

Automated Lithuanian Post Logistics Center

Finished

“Vilniaus Baldai” Factory in Trakai District (Value – 50 Million Euros)

Finished

“Litgrid” system control and data center

Finished

Automated “Continental Automotive” factory in the FEZ of Kaunas

Finished

“Creolink” Warehouse With Administrative Premises

Finished

The Construction of 2 Modules of “Hegelmann Transporte” Logistics Complex

Finished

A Modern Food Production Manufactory of “Vilnius Poultry Farm” in Rudamina

Finished

“Ogisanda” Warehouse & Administration Building

Finished

“Hansa Flex Hidraulika” Administrative, Industrial & Warehouse Building

Finished

Class A Logistics Center of „Liepkalnis Industrial Park”

Finished

“Kaišiadorys Poultry Farm” Bird Breeding Complex

Finished

Fire and Rescue Training Center

Finished

“Brenntag Lithuania” Warehouse & Administration Building

Finished

“ABB” High Voltage Switchgear in Alytus

Finished

„Alviva“ Sewing Factory

Finished

„Entafarma“ Pharmaceutical Warehouse & Administration Building

Finished

“Grainmore” Automated Probiotic Processing Plant & Laboratory

Finished

The Reconstruction of Industrial Sewing Building “Lelija”

Finished

“Schmitz Cargobull Baltic” Production Building

Finished

Eišiškės Border Control Point

Finished

The Extension of “WOOD LINE” Warehouse

Finished

The Reconstruction of “Galinta & CO” Production Lines

Finished

Fire and Rescue Department

Finished

“Airo Catering Services Lietuva” Cooking Manufactory